Fibre optic upgrade – 2232% faster speeds

Back To Results
  • National utilities company

Peak Technology Solutions was chosen by a UK leading utilities company to undertake a large scale, fully integrated fibre optic network upgrade.

History

The existing DH+ network on the Sewage Treatment site was operating at 97% capacity. A robust solution was required utilising new equipment and technologies.

The site Programmable Logic Controllers (PLC) communicated via a legacy DH+ (data highway plus) network protocol alongside the site SCADA. The stress on the existing network meant continual dropped data packets and false alarms.

The aim was for Peak to upgrade the DH+ network site-wide to a fibre optic ring.

Solution

The scale of the fibre optics project required careful planning of future network points, considering peripheral site upgrades. Peak completed a front-end engineering study (FEED) to depict the best solution.

Peak installed 17 “network node boxes”, housing managed fibre/ethernet switch for future adjacent PLC connection.

Sub-fed from the network node boxes were three DLRs (Device Level Rings), each providing a secondary network layer to process areas with multiple PLC’s.

Peak completed the Principal Designer & Contractor role as per CDM regulations 2015, overseeing multiple site contractors during the construction phase.

Peak implemented a fully integrated fibre optic network with multiple appropriate network node points. An estimated 4.5 kilometres of fibre optic cable was installed as part of the project.

Result

The Sewage Treatment Works fibre optic upgrade was a huge success and the site SCADA speed has improved and become more robust.

The designed “network node boxes” installed by Peak have now been put forward as the benchmark for the client standard.

Security considerations and standards have been achieved by using industrial managed network equipment, configured as per client protocols and whilst on site, Peak achieved a 100% site UVDB score.

As a wider implication of the work, the additional local fibre optic connection points for all site PLC’s has also activated separate projects, which were awaiting an improved network topology.

 

“Peak demonstrated their ability on the fibre upgrade project to comprehensively design, and offer consultancy, to deliver a project intending to future proof the site. The front-end study was beneficial and allowed for smooth programme delivery.

Peak performed the principal contractor role during the commissioning phase. During this time, they received a 100% UVDB score which was a testament to the safety considerations for their principal project role”

 

Regional Systems Engineer, Utilities Client

Related Case Studies

Automation control for a utilities client

  • SECTOR: Utilities
View
Automation Control - Edwin James Group

Related Case Studies

Delivery of IEC 61508 & IEC 61511 compliant system

  • SECTOR: Industrial Manufacturing
View
IEC 6508 & IEC 61511 - Edwin James Group

CONTACT US

To get in touch, please complete the form below: