Delivery of IEC 61508 & IEC 61511 compliant system

Back To Results
  • Global chemicals, crop protection and chemicals company

Peak Technology Solutions undertook the delivery of a Safety Instrumented Systems compliant to IEC 61508 and IEC 61511 for a global chemicals company.

History

As part of a major process refurbishment, Peak was engaged for the the delivery of a control solution including BPCS (Basic Process Control System) and Safety Instrumented System for a process plant used to manufacture Bicarbonate Soda to pharmaceutical grade.

Solution

The fast-track nature of the project guided Peak’s technology selection: a programmable safety instrumented system (Rockwell Guardlogix) that allowed the team to design and build the electrical infrastructure whilst the process design was still in progress. A more conventional system design using hardwired safety would have inherited longer development time, requiring as a pre-requisite the completion of the process design and associated SIF identifications.

The system implemented included:

  • Rockwell GuardLogix and distributed Safety Point I/O for the SIS
  • Rockwell Dual Redundant ControlLogix and distributed Flex I/O for the BPCS
  • Industrial Network Connectivity and VLANS using Rockwell Stratix Switches and Ring topology
  • Redundant Rockwell Factorytalk View SCADA

Infrastructure and clients IEC 61511 Life cycle was followed with Peak delivering the following scope:

  • Participation to Hazard and Risk Assessment
  • Identification of Safety Instrumented Functions
  • Design and Assembly of Hardware Architecture
  • Design and development of Safety Logic
  • Production of Safety Requirement Specifications
  • Testing and Validation
  • Site Installation and verification
  • Proof Testing procedures

Over 30 SIFs were identified and targeted to the relevant SIL level. The safety logic solver interfaces with the BPCS to provide a detailed status of the SIS integrity

Results

A successful project delivered under challenging time constraints through Peak’s ability to work as a combined team with the customer.

The safety system is implemented under the 61511 SIS Safety Lifecycle and Functional Safety Assessment Phases and provides the required level of protection.

The selection of a programmable safety system introduced a level of flexibility between the various project disciplines as changes and introduction to new SIFs became possible as the process design evolved.

The outcome contributed to safeguarding the employment of a local team

Related Case Studies

Process safety for a large chemical distribution client

  • SECTOR: Industrial Manufacturing
View
Industry 4.0 - Edwin James Group

Related Case Studies

Replacing legacy system for National utility client

  • SECTOR: Utilities
  • DURATION: 12 months
View
Replacing Legacy Systems - Edwin James Group

CONTACT US

To get in touch, please complete the form below: